HomeMy WebLinkAboutSan Bernardino - Letter from Mandeville (Closed Session Item B)June 25, 2025
Dear Members of the San Bernardino City Council,
I hope this message finds you well. I am writing on behalf of Mandeville Modular to formally
address the outstanding invoices due (Invoice Nos. 151689 and 200512), to outline several
ongoing challenges affecting project progress at the San Bernardino Hope Campus, and to
respectfully seek the City’s support in helping move this vital project forward. We have
approached this work in the spirit of partnership and collaboration, striving at every turn to
deliver on our commitments and accommodate evolving project needs. Unfortunately, it
increasingly feels that these efforts have not been fully reciprocated by CREDE or, at times, by
the City, leaving Mandeville in a difficult position as we work to keep the project on track.
Throughout this process, Mandeville Modular has remained deeply committed to being a
collaborative and solutions-oriented partner. We have fully fulfilled our obligations under the
Design Services and Purchase Agreement dated December 4, 2024, and have worked
diligently—often beyond our contractual scope—to maintain momentum on the project.
Specifically, our invoices (151689 dated May 7, 2025, and 200512 dated June 5, 2025) reflect
services rendered and deliverables provided in strict adherence to the approved phased work
plan (Exhibit B-2). These include completion of the Schematic Plan Phase, Design Development
Phase, Final Working Drawings & Specifications Phase, and corresponding project management
services through May 2025. In line with Section 3.10.4 of our contract, payment for these
phases is due within thirty (30) days of submission. To date, no deficiencies have been identified
that would justify withholding payment on these invoices, and we respectfully request the City’s
support in ensuring these are processed promptly.
It is important to share that while we have maintained our commitment to collaboration and
flexibility, we are increasingly encountering challenges that make this effort feel one-sided.
Mandeville has accommodated numerous requests that extend beyond our contracted scope,
including the design and integration of a commercial kitchen at no additional cost, as well as
support for budgetary tracking and reporting that is not required by our agreement. We have
done so in good faith to support the project’s broader success, but these accommodations are
contributing to strain on our team without reciprocal clarity or support.
Moreover, despite our collaborative intent, Mandeville has at times been left out of key project
coordination opportunities—such as Owner-Architect-Contractor (OAC) meetings—and has not
been consistently informed when critical project leaders are out of office, creating further
uncertainty in communication and decision-making.
It is important to highlight CREDE’s contractual obligations under its Professional Services
Agreement with the City, dated December 4, 2024, and the extent to which these obligations
have not been met, resulting in significant delays to the project. CREDE, as Development
Manager, is responsible for providing timely and competent project management services,
ensuring adherence to project schedules, and facilitating clear and consistent communication
among all stakeholders. However, CREDE has failed to issue or circulate an updated and final
project schedule despite repeated requests and despite it being a fundamental requirement for
proper project coordination. As it stands, the only approved schedule remains the original
project schedule executed alongside the contract in December 2024. The absence of a current,
ratified schedule has caused widespread confusion and disruption, impeding our ability to align
factory production timelines and on-site preparations. Furthermore, Mandeville submitted a $0
change order in March 2025 to formally document the City-induced delays—delays that have
now exceeded 120 days. Despite our good faith efforts to gain clarity on revised start dates and
milestones, CREDE has repeatedly vacillated on key dates and has not facilitated final approval
of this change order, further exacerbating project delays and financial exposure.
These delays and mismanagement issues are further compounded by CREDE’s failure to provide
an updated project organizational chart, as required to ensure transparency and accountability
in communication lines. The original organizational chart contains outdated contacts, and the
lack of a revised document has significantly hampered clear and timely correspondence
between the various consultants, contractors, and City representatives. This omission violates
the basic duty of care expected of CREDE under its agreement with the City and under standard
project management practices.
We must also address the performance of CREDE’s assigned Project Manager, whose lack of
experience as a Project Manager have materially hindered progress. The ongoing indecision,
contradictory directives, and unreasonable requests from CREDE’s Project Manager meet this
threshold. This is further underscored by the Civil Design Proposal that CREDE’s Project
Manager transmitted to Heith Bibby, President of Mandeville Modular, which notably requested
100% upfront payment of their contract. This request not only departs from standard industry
practices but raises serious concerns regarding financial stewardship and risk management on
this publicly funded project.
Mandeville Modular has consistently demonstrated collaboration and flexibility well beyond our
contractual obligations. We have diligently attended and contributed to weekly design
meetings, though it is important to note that our contract does not stipulate these as the
exclusive or mandatory forum for resolving broader project execution matters. Specifically,
Section 3.7.8 of our Agreement speaks to coordination of services, with an expectation that the
City and its agents will provide appropriate forums and guidance to resolve major outstanding
items such as project scheduling, organizational structure updates, and scheduling of factory
inspections.
Given these circumstances, Mandeville Modular requests immediate action by the City to
resolve these matters. Specifically, we seek (1) immediate payment of Invoices 151689 and
200512 in accordance with the terms of our contract, (2) finalization and execution of the
outstanding $0 change order to formally account for project delays to date, and (3) the
scheduling of a comprehensive project coordination meeting led by the City to finalize the
project schedule, organizational chart, and address other outstanding items essential to project
delivery.
We want to emphasize that Mandeville remains fully committed to this project and to our
partnership with the City. Our sole objective is to deliver a high-quality facility that meets the
community’s needs. We respectfully ask for your leadership in resolving the administrative and
contractual obstacles that are preventing progress.
We look forward to your confirmation of payment processing and to receiving a proposed date
for a coordination meeting at your earliest convenience. Should the City require any additional
documentation to facilitate these next steps, we stand ready to provide it.
Sincerely,
Mandeville Modular